What is Yellowstone Club doing to make sure this won’t happen again?

We are continuing to evaluate the best approach to the repair. We have submitted a plan to MDEQ and other stakeholders and are awaiting feedback and input. They were onsite with us on March 9, 2016. We are hopeful to start rebuilding the outlet structure on March 16th pending the MDEQ approval. The repair design has additional engineered features that will further minimize the risk of this occurrence in the future. The new design also incorporates several additional monitoring devices which will allow the operator to evaluate the performance of the pond easier.